      Issue Summary

      When a Team Objective is created, be it Feature Finisher or Milestone, if Target Completion is added, the Objective will appear duplicated on the Program Board for that Program + PI.
      See one example, where Objective 647 only has the Target Sync Sprint:

      And when the Target Completion Date is added:

      Steps to Reproduce

      1. Create a Team Objective
      2. Fill the Program + PI
      3. Add a Target Sync Sprint
      4. Add a Target Completion Date that is inside the Sprint
      5. Now go to the Program Board
      6. On Tier 1/Config Bar select the Program + PI
      7. See the Objective duplicated

      Expected Results

      The Objective will only appear once.

      Actual Results

      The Objective appears duplicated

      Workaround

      Currently there is no known workaround for this behavior. A workaround will be added here when available

        1. board_2.png
          382 kB
          Diego Larangeira
        2. objective_2.png
          504 kB
          Diego Larangeira
        3. objective_1.png
          548 kB
          Diego Larangeira
        4. board_1.png
          358 kB
          Diego Larangeira

            4f593be5d819 Anna Eshlin De Kassal (Inactive)
            a8cff3407f0b Diego Larangeira
            Votes:
            4 Vote for this issue
            Watchers:
            10 Start watching this issue

              Created:
              Updated:
              Resolved: