Issue Summary
The pop-up provided for team velocity calculations in the Program Room are confusing when velocity overrides are used.
It would be great if override velocity values are loaded for one or more sprints to show each sprint with its velocity and OR or AV for override or average.
Screenshot attached
Steps to Reproduce
Navigate to the Program Room
Look for the Team load section in the room
Hover over a team load to get information on how the number was calculated.
Expected Results
The explanation should be clearer,
"All sprints are loaded with planned velocities and the total Program Increment velocity is 89 points. No Average Velocities were used."
Actual Results
The pop-ups are confusing and it is challenging to figure out how the loads have been cal
Workaround
Currently there is no known workaround for this behavior. A workaround will be added here when available