Time estimates for sub tasks are not added to the total estimate of a Story in the Plan and Work view.

    • Icon: Suggestion Suggestion
    • Resolution: Fixed
    • 6.0.3
    • AgileBoard
    • - Configure Rapid board with "Original Time Estimate" as the Estimation Statistic.
    • We collect Jira feedback from various sources, and we evaluate what we've collected when planning our product roadmap. To understand how this piece of feedback will be reviewed, see our Implementation of New Features Policy.

      NOTE: This suggestion is for JIRA Software Server. Using JIRA Software Cloud? See the corresponding suggestion.

      When adding sub-tasks with estimations, the Estimation field in the Plan and Work mode are not cumulative.

      Steps:
      1- Add a Story to back log.
      2- Add a Sub Task with 8hrs estimate to that Story
      3- Notice that on the Sprint Marker the "Estimate" field is not updated. Same for the Template view on the right side..

      • If you open the Story outside of the Rapid Board then the time tracking is cumulative.
      • Refer to attachment for a screenshot. The screenshot does not show the Original Estimation for the Sub Task, but it is set to 8hrs.

          Form Name

            [JSWSERVER-5283] Time estimates for sub tasks are not added to the total estimate of a Story in the Plan and Work view.

            It's 2018 and this remains broken. Nice work 

            Rutger Schaafsma added a comment - It's 2018 and this remains broken. Nice work 

            Any solution for this request? Has anyone come up with a workaround using a plugin? If yes, what plugins would you recommend for Jira Server?

            Bojana Mandic added a comment - Any solution for this request? Has anyone come up with a workaround using a plugin? If yes, what plugins would you recommend for Jira Server?

            Mark Green added a comment -

            We just bumped into this as well.  Will this ever be addressed?
            If not, we'll have to abandon using sub-tasks (boo) to have velocity and estimating accurate in Jira.

            Mark Green added a comment - We just bumped into this as well.  Will this ever be addressed? If not, we'll have to abandon using sub-tasks (boo) to have velocity and estimating accurate in Jira.

            Agreed, as we mature our Agile environments, this is really needed.

              • Support can you provide an update on this? Please and thank you!

            Janene Hoffmann added a comment - Agreed, as we mature our Agile environments, this is really needed. Support can you provide an update on this? Please and thank you!

            This is still a very significant pain point for us in using this software. It is not possible to use this tool for load balancing during sprint planning. Could we get a comment as to if this is something that we can expect a fix for some day? Or can we assume we will never be able to use JIRA for all of our sprint planning work?

            Brian Hayes added a comment - This is still a very significant pain point for us in using this software. It is not possible to use this tool for load balancing during sprint planning. Could we get a comment as to if this is something that we can expect a fix for some day? Or can we assume we will never be able to use JIRA for all of our sprint planning work?

            Michael added a comment -

            Is there any update on this item? This is a huge problem for us. Not being able to see the total estimate on the plan board forces me to manually add up time which is very time consuming.

            Michael added a comment - Is there any update on this item? This is a huge problem for us. Not being able to see the total estimate on the plan board forces me to manually add up time which is very time consuming.

            Could someone from atlassian tell us if this is going to be fixed please?

            The simple fact that when planning, the parent story has a blank estimate field makes it useless... it's particularly frustrating, since everywhere else in JIRA the estimated time for a story always includes it's subtasks.

            Please make it consistent!

            Joseph Narai added a comment - Could someone from atlassian tell us if this is going to be fixed please? The simple fact that when planning, the parent story has a blank estimate field makes it useless... it's particularly frustrating, since everywhere else in JIRA the estimated time for a story always includes it's subtasks. Please make it consistent!

            AL added a comment -

            This issue appears to have regressed as of JIRA Agile 6.3.12 on JIRA 6.2.

            AL added a comment - This issue appears to have regressed as of JIRA Agile 6.3.12 on JIRA 6.2.

            klavergne added a comment -

            Not fixed in GreenHopper v6.2.3.

            klavergne added a comment - Not fixed in GreenHopper v6.2.3.

            Still in JIRA Agile 6.3.4 the sum of original estimates is not shown for each individual story.
            The sum of original estimates is visible in a bar below, but not in each of the story.

            Do you think it's a separate issue?
            Or may you please reopen this one

            Best,
            Maxym

            Maxym Mykhalchuk added a comment - Still in JIRA Agile 6.3.4 the sum of original estimates is not shown for each individual story. The sum of original estimates is visible in a bar below, but not in each of the story. Do you think it's a separate issue? Or may you please reopen this one Best, Maxym