Description
Issue Summary
When using Original Time Estimate on a board for Estimation, the Velocity Chart will show time in seconds rather than hours or minutes.
Steps to Reproduce
- Create a few issues in a board and modify the Estimate field on the issue to be in hours or minutes.
- Start a sprint and add these issues to them.
- Complete the sprint and open up the Velocity Chart once complete.
Expected Results
The Velocity chart will show the committed and completed time for issues to be within hours or minutes.
Actual Results
The time for these values shows up in seconds instead:
Workaround
Use a different Estimation statistic such as Story Points for the board.
Notes
I found that this issue could not be reproduced in Jira 8.3.0. It's possible this is due to the change in the Velocity Chart changes that were made in 8.9.0
Attachments
Issue Links
- relates to
-
JSWSERVER-20700 Add an option to customize the time unit format for the Velocity Chart Y axis original time estimate
- Gathering Interest
- is cloned by
-
FLASH-2479 Loading...
-
MNSTR-4580 Loading...
- mentioned in
-
Page Loading...