NOTE: This bug report is for JIRA Software Server. Using JIRA Software Cloud? See the corresponding bug report.
Summary
Issues that ties to a previous Completed sprint and added to current active sprint does not appear on the Sprint report if the issue is removed from Active Sprint.
Steps to Reproduce
- Create sprint A
- Put issue 1 in Sprint A
- Start and close sprint A without completing issue 1. Issue 1 will go to the backlog.
- Create sprint B
- Put issue 1 and 2 in sprint B
- Start sprint B
- Remove both issues from sprint B
Expected Results
The Sprint report would show the issue 1 and 2 under "Issues Removed From Sprint"
Actual Results
The sprint report only show issue 2 as removed from Sprint and issue 1 is missing.
Workaround
No known workaround at this time.
Note
Affecting issues that contain a previous Completed sprint.
- duplicates
-
JSWSERVER-15541 The burndown chart is not showing the information when an issue is removed from the sprint.
- Closed
- is related to
-
JSWSERVER-13783 Velocity report should only show sprints related to the current board
- Closed
- relates to
-
JSWSERVER-20815 Issue removed from Sprint not showing in Burndown Chart or Sprint Report when moving from Sprint to Sprint
- Closed