The burndown chart is not showing the information when an issue is removed from the sprint.

XMLWordPrintable

    • Type: Bug
    • Resolution: Fixed
    • Priority: Low
    • 8.5.5, 8.8.1, 8.9.0
    • Affects Version/s: 7.2.2, 7.3.0, 7.7.0, 7.11.2
    • Component/s: None
    • 7.02
    • 16
    • Severity 3 - Minor
    • 5

      Summary

      The burndown chart is not showing the information when an issue is removed from the sprint.

      Steps to Reproduce

      1. create sprint A
      2. put issue 1 in sprint A
      3. start and close sprint A without completing issue 1
      4. create sprint B
      5. put issue 1 and 2 in sprint B
      6. start sprint B
      7. remove both issues from sprint B

      Expected Results

      Burndown chart shows both issue 1 and issue 2 as being removed from sprint B

      Actual Results

      Burndown chart only shows issue 2 as being removed from sprint B

      Notes

      • This is affecting issues that don't have an estimation.
      • Seems to be only affecting Original Time Estimate & Original Story Points estimation only.
      • Issue Type such as Task is not affected.

      Workaround

      • Workaround 1 (Original Story Points)
        The only known workaround for now is to put the issue back in the Sprint after removal and then remove again
      • Workaround 2 (Original Time Estimate)
        Assign 0m to the issue's estimation will keep it in the report.

            Assignee:
            Stanislav Natkovskyi (Inactive)
            Reporter:
            Ruchi Tandon (Inactive)
            Votes:
            68 Vote for this issue
            Watchers:
            51 Start watching this issue

              Created:
              Updated:
              Resolved: