Issue Summary
Forecast -> Plan Capacity -> 'Current FTE' calculation is considering deactivated users.
Steps to Reproduce
- Login
- Browse to a Program's agile team to notice current Team member allocations
- Deactivate an user from the team
- Notice at Team member allocations reflect correct number of users
- Browse to Forecast -> Plan Capacity
- Observe the results
Expected Results
Plan Capacity -> 'Current FTE' calculation does not consider deactivated users
Actual Results
Plan Capacity -> 'Current FTE' calculation considers deactivated users as well.
Workaround
Remove the deactivated user from all assigned teams.