Type:
Suggestion
-
Resolution: Unresolved
-
Component/s: Apps - Migration Assistant
-
None
-
3
Issue Summary
User submitted a cancel after App migration spending several hours. The status change is very slow.
This is reproducible on Data Center: Yes
Steps to Reproduce
- Migrate App using JCMA
Expected Results
Cancelled by user should be reflected more quickly than the current operation. Also, the status in JCMA should reflect the actual status of the app migration more effectively.
Actual Results
The app migration status in JCMA will show 0% RUNNING state for very long time, even though the user clicked the cancel button.
Workaround
Check the migration logs to confirm the status of the app migration.
- is related to
-
MIG-1992 Migrating Zephyr Squad using JCMA shows 0% Cancelled status even though the migration is still running
-
- Gathering Impact
-