    Description

      NOTE: This bug report is for JIRA Software Server. Using JIRA Software Cloud? See the corresponding bug report.

      The calculation of the scope change is sometimes not correct.

      Steps to reproduce

      1. Create a sprint in Plan Mode
      2. Create 5 issues with an estimate of '2' each.
      3. Add all 5 issues to the future sprint.
      4. Remove one of the issues from the future sprint.
      5. Start the sprint with the remaining 4 issues.
      6. Look at the Sprint Health Gadget - the scope change amount will be 0%.
      7. Remove another issue from the sprint.
      8. Look at the Sprint Health Gadget again.

      Expected

      The scope change amount should be -25% – 8 points originally in scope, and 2 were removed.

      Actual

      The scope change amount is -40%.

      Attachments

        Issue Links

          Activity

            People

              Unassigned Unassigned
              melias MichaelA (Inactive)
              Votes:
              3 Vote for this issue
              Watchers:
              8 Start watching this issue

              Dates

                Created:
                Updated:
                Resolved: