      We have a Scrum board which includes issues with subtasks. Both parent and subs have time estimates. JIRA's timetracking is set to include subtasks. The burndown chart ignores the subtasks' time values though and only displays the parent value.

        1. gh-burndown1.png
          gh-burndown1.png
          88 kB
        2. gh-burndown0.png
          gh-burndown0.png
          26 kB

            [JSWSERVER-7459] Subtask time estimate rollup is ignored in burndown chart

            At the moment, Sub-tasks estimates aren't counted into the parent estimate in JIRA Agile - therefore the behaviour reported in this ticket is expected. A related story, GHS-9167, is a request to change the calculation and account for sub-task estimates in the parent issue.

            More details on estimation and tracking can be found in this blog post: Time Estimates with Sub-Tasks, and the related Answers thread.

            Dobroslawa Wierzbicka (Inactive) added a comment - At the moment, Sub-tasks estimates aren't counted into the parent estimate in JIRA Agile - therefore the behaviour reported in this ticket is expected. A related story, GHS-9167 , is a request to change the calculation and account for sub-task estimates in the parent issue. More details on estimation and tracking can be found in this blog post: Time Estimates with Sub-Tasks , and the related Answers thread .

            Currently working as intended

            Peter Obara added a comment - Currently working as intended