We have a Scrum board which includes issues with subtasks. Both parent and subs have time estimates. JIRA's timetracking is set to include subtasks. The burndown chart ignores the subtasks' time values though and only displays the parent value.
- relates to
-
JSWSERVER-13138 Sum estimates from sub-tasks in user stories
- Gathering Interest
-
JSWSERVER-9167 Provide ability to automatically sum estimates from sub-tasks in user stories
- Future Consideration
At the moment, Sub-tasks estimates aren't counted into the parent estimate in JIRA Agile - therefore the behaviour reported in this ticket is expected. A related story, GHS-9167, is a request to change the calculation and account for sub-task estimates in the parent issue.
More details on estimation and tracking can be found in this blog post: Time Estimates with Sub-Tasks, and the related Answers thread.