Guideline end point at Version Start Date should respect corrections made to "Original Estimate" field.

    • Icon: Suggestion Suggestion
    • Resolution: Answered
    • None
    • None
    • We collect Jira feedback from various sources, and we evaluate what we've collected when planning our product roadmap. To understand how this piece of feedback will be reviewed, see our Implementation of New Features Policy.

      NOTE: This suggestion is for JIRA Software Server. Using JIRA Software Cloud? See the corresponding suggestion.

      Since I can edit the "Original Estimate" field of each story/subtask any time during the sprint (like when estimating was done on story cards, and I'm entering the estimates the day after start of sprint), I would expect the sprint start endpoint of the guidline to reflect the total of all "Original Estimate" fields' CURRENT VALUES (not shouting; just emphasizing).

      I just started a 90 point sprint, entering most estimates on day 2, but my guideline says it's a 2 point sprint, so it's useless.

      (I disagree with other users who want the guidline to be the guideline for work remianing. I want to know where my original estimate guideline is, so I know how far off plan discovery has driven me, so I can adapt the depth of my work and my plan to hit the end date.)

      Thanks! Great tool!

            [JSWSERVER-4417] Guideline end point at Version Start Date should respect corrections made to "Original Estimate" field.

            Katherine Yabut made changes -
            Workflow Original: JAC Suggestion Workflow [ 3068849 ] New: JAC Suggestion Workflow 3 [ 3658927 ]
            Status Original: RESOLVED [ 5 ] New: Closed [ 6 ]
            Owen made changes -
            Workflow Original: Confluence Workflow - Public Facing v4 [ 2625680 ] New: JAC Suggestion Workflow [ 3068849 ]
            Rachel Lin (Inactive) made changes -
            Workflow Original: JIRA PM Feature Request Workflow v2 - TEMP [ 2327674 ] New: Confluence Workflow - Public Facing v4 [ 2625680 ]
            Status Original: Closed [ 6 ] New: Resolved [ 5 ]
            Katherine Yabut made changes -
            Workflow Original: JIRA PM Feature Request Workflow v2 [ 2044517 ] New: JIRA PM Feature Request Workflow v2 - TEMP [ 2327674 ]
            Katherine Yabut made changes -
            Workflow Original: JIRA PM Feature Request Workflow v2 - TEMP [ 2032750 ] New: JIRA PM Feature Request Workflow v2 [ 2044517 ]
            Katherine Yabut made changes -
            Workflow Original: JIRA PM Feature Request Workflow v2 [ 737721 ] New: JIRA PM Feature Request Workflow v2 - TEMP [ 2032750 ]
            jonah (Inactive) made changes -
            Description Original: Since I can edit the "Original Estimate" field of each story/subtask any time during the sprint (like when estimating was done on story cards, and I'm entering the estimates the day after start of sprint), I would expect the sprint start endpoint of the guidline to reflect the total of all "Original Estimate" fields' CURRENT VALUES (not shouting; just emphasizing).

            I just started a 90 point sprint, entering most estimates on day 2, but my guideline says it's a 2 point sprint, so it's useless.

            (I disagree with other users who want the guidline to be the guideline for work remianing. I want to know where my original estimate guideline is, so I know how far off plan discovery has driven me, so I can adapt the depth of my work and my plan to hit the end date.)

            Thanks! Great tool!
            New: {panel:bgColor=#e7f4fa}
              *NOTE:* This suggestion is for *JIRA Software Server*. Using *JIRA Software Cloud*? [See the corresponding suggestion|http://jira.atlassian.com/browse/JSWCLOUD-4417].
              {panel}

            Since I can edit the "Original Estimate" field of each story/subtask any time during the sprint (like when estimating was done on story cards, and I'm entering the estimates the day after start of sprint), I would expect the sprint start endpoint of the guidline to reflect the total of all "Original Estimate" fields' CURRENT VALUES (not shouting; just emphasizing).

            I just started a 90 point sprint, entering most estimates on day 2, but my guideline says it's a 2 point sprint, so it's useless.

            (I disagree with other users who want the guidline to be the guideline for work remianing. I want to know where my original estimate guideline is, so I know how far off plan discovery has driven me, so I can adapt the depth of my work and my plan to hit the end date.)

            Thanks! Great tool!
            jonah (Inactive) made changes -
            Link New: This issue relates to JSWCLOUD-4417 [ JSWCLOUD-4417 ]
            Martin (Inactive) made changes -
            Workflow Original: GreenHopper Kanban Workflow v2 [ 362128 ] New: JIRA PM Feature Request Workflow v2 [ 737721 ]
            Issue Type Original: Story [ 16 ] New: Suggestion [ 10000 ]
            Priority Original: Minor [ 4 ]
            Status Original: Resolved [ 5 ] New: Closed [ 6 ]
            Michael Tokar made changes -
            Resolution New: Answered [ 9 ]
            Status Original: Open [ 1 ] New: Resolved [ 5 ]

              Unassigned Unassigned
              16058a7a9bc9 Marc Trudeau
              Votes:
              0 Vote for this issue
              Watchers:
              1 Start watching this issue

                Created:
                Updated:
                Resolved: