Support different types of scheduling dependencies

XMLWordPrintable

    • 1
    • 2
    • We collect Jira feedback from various sources, and we evaluate what we've collected when planning our product roadmap. To understand how this piece of feedback will be reviewed, see our Implementation of New Features Policy.

      NOTE: This suggestion is for JIRA Portfolio Server. Using JIRA Portfolio Cloud? See the corresponding suggestion.

      Currently Portfolio supports only one type of dependency which is "B can start as soon as A is completed".

      Add support for other dependencies such as Start to Finish, Finish to Finish, Start to Start, Finish to Start, or a partial overlap such as "can start when 50% is completed"

      Additionally, support configuration to set the delay such as number of days before the start of another Epic/Story.