Bug
-
Resolution: Fixed
-
Medium
-
None
-
Archived Jira Software Cloud
-
None
-
9
-
Severity 2 - Major
-
NOTE: This bug report is for JIRA Software Server. Using JIRA Software Cloud? See the corresponding bug report.
Summary
Issues removed from an active sprint (either into a next planned sprint or backlog) do not appear under "Issues Removed from Sprint" in the Sprint Report and the Burndown Chart does not show Scope Change
Environment
- JIRA v1000.35.2
Steps to Reproduce
- Create a Sprint in a JIRA Software Project
- Add Issues to the Sprint
- Start Sprint
- Move issues from the Active Sprint into either another Planned Sprint or the Backlog
- View Sprint Report or Burndown Chart
This is seen in instances with Parallel Sprints both enabled and disabled
Expected Results
Both the Sprint Report and Burndown Chart should show Scope Change where these issues are being removed.
Actual Results
No errors in the logs
Notes
If the Moved Issues are re-added, the Burndown Chart shows scope change; the Sprint Report shows the Issues as Incomplete.
Workaround
none
- is related to
-
JSWSERVER-15541 The burndown chart is not showing the information when an issue is removed from the sprint.
- Closed
- relates to
-
JSWCLOUD-13810 Issues removed from active sprint are no longer shown in the Sprint Report or Burndown Chart
- Closed
-
JSWSERVER-15747 Issues removed from sprint not showing up in Agile Reports after upgrade
- Gathering Impact