In the backlog view for a sprint, Remaining time is not showing in hours and is not an accurate representation.
Steps to reproduce
1. Create a sprint
2, Populate sprint with stories, tasks, and subtasks
3. Populate "Original Estimate" for all stores in amount of 200 hours or greater
4. See "Remaining" estimate at bottom of sprint
Expected Result:
See remaining hours ("225.5h")
Actual Result
See unusable value broken out into weeks and day ("7w 2d 30m")
Notes
This value is incredibly incorrect as 7w 2d 30 m would be 296.5 hours ((7*40) + (2*8) + (.5) = 296) while our sprint actually adds up to 225.5 hours.
- is duplicated by
-
JSWCLOUD-15949 Estimate and remaining time at Backlog page does not set to 'Hours' format
-