-
Type:
Bug
-
Resolution: Duplicate
-
Priority:
Medium
-
None
-
Affects Version/s: 6.3.9
-
Component/s: AgileBoard
-
Environment:
standalone
-
6.03
Times in the sub task are not displayed in the Agile planning mode
Test Steps:
1) Create a story
2) Create a sub task in this story
3) In the sub task the original estimate = 2h
4) The time from all sub task in the story shown correctly
5) Create a Sprint
6) Move this story to this sprint
Expected Result:
The time from all sub task in the story shown correctly
Actual Result:
Under the sprint I don’t see the original estimate (see screenshot)
- duplicates
-
JSWSERVER-7719 Sum of remaining estimate on sub-tasks not displayed on user story in agile boards
- Future Consideration