-
Bug
-
Resolution: Fixed
-
High
NOTE: This bug report is for JIRA Software Cloud. Using JIRA Software Server? See the corresponding bug report.
When trying to complete a sprint that has unresolved sub-tasks, instead of automatically removing these issues to the backlog Greenhopper gives error:
"Sprint cannot be completed as there are incomplete subtasks in the following issue: ..."
Workarounds:
There are two possible workarounds for this problem:
- Manually remove those from the sprint - https://confluence.atlassian.com/display/GH/Removing+an+Issue+from+a+Sprint
or - Close off the subtask issue that's caught, then reopen it to put it in the next sprint
- duplicates
-
JSWCLOUD-9418 JIRA 6.1: cannot complete sprint with open subtasks on open issue
- Closed
- is related to
-
JSWSERVER-9512 Unable to complete sprint because sub-task is not resolved
- Closed
-
JSWCLOUD-7232 Unable to complete a sprint if sub-task status is not included in the Done column
- Closed
- relates to
-
JSWCLOUD-12012 Unable to close Sprint with closed parent issue and open sub-tasks
- Gathering Interest