          [JSWCLOUD-8085] Non working days not taken into account

          on GHS-6466-days-remaining-gadget

          Nikolay Petrov (Inactive) added a comment - on GHS-6466 -days-remaining-gadget

          Calendar days but no non-working days, correct. So, to use the example from our discussion of Mon being the end of sprint, the entire Friday it's 1 day left, Sat and Sun it's 1 too and on Mon it becomes 0 - regardless of time the sprint ends. Oh and we ignore timezone issue.

          Tom Kotecki (Inactive) added a comment - Calendar days but no non-working days, correct. So, to use the example from our discussion of Mon being the end of sprint, the entire Friday it's 1 day left, Sat and Sun it's 1 too and on Mon it becomes 0 - regardless of time the sprint ends. Oh and we ignore timezone issue.

          tkotecki Hey Tom - we did decide on "Calendar days", which in turn means no "non-working days" right?

          Nikolay Petrov (Inactive) added a comment - tkotecki Hey Tom - we did decide on "Calendar days", which in turn means no "non-working days" right?