Bug
-
Resolution: Duplicate
-
Low
-
None
Summary
When Time Tracking is set to Display In hours the estimates values are displayed in Pretty
EXE:
- 25.5 hours is displayed as 3d 1h 30m
- 15 min displays as 15m rather than .25h
Environment
- JIRA v7.1.0-OD-05-006
- JIRA Agile v7.1.14-D20160120T021005
Steps to Reproduce
- On Agile Board
- Configure time Tracking to use HOURS as described in:
- https://confluence.atlassian.com/jiracloud/configuring-time-tracking-735940583.html
The number of working hours per day is 8.
The number of working days per week is 5.
Time estimates will be displayed in the following format: hours (e.g. 36.5h)
The current default unit for time tracking is hour.
Copying of comments to work description is currently enabled.
- https://confluence.atlassian.com/jiracloud/configuring-time-tracking-735940583.html
- Create Issue with an original estimate of 25.5 hours
- Add to Sprint
Expected Results
Agile Board time tracking time tracking estimates will display 25.5h
Actual Results
Time Tracking Displays 3d 1h 30m
Workaround
There is no Workaround At this time
- is duplicated by
-
JSWCLOUD-15949 Estimate and remaining time at Backlog page does not set to 'Hours' format
-
- Closed
-