Changing calendar settings doesn't affect calendars within JIRA Agile

XMLWordPrintable

    • 3
    • Severity 2 - Major

      Summary

      When changing configuration related to the calendars at JIRA Administration > System, some changes doesn't take place within JIRA Agile.

      Environment

      JIRA Cloud

      Steps to Reproduce

      Change calendar configuration format as per Customizing the Look and Feel, in the section Date/Time format:

      1. Go to JIRA Administration > System > Look and Feel
      2. Set Date/Time format to 24 hours yyyy-MM-dd HH:mm
      3. Check the box at the bottom to make Monday first day of the week, as per How to set Monday as First Day of Week
      4. Go to JIRA Administration > System > General Configuration > Advanced Settings and enter the format (sysadmin only):
      • jira.date.time.picker.java.format: yyyy-MM-dd HH:mm
      • jira.date.time.picker.javascript.format: %Y-%m-%d %H:%M

      Expected Results

      Calendars will be showing Monday as first day of the week, and time will be displayed in 24 hours format

      Actual Results

      Calendars within JIRA Agile are still showing Sunday as first day of the week and am/pm format (see screenshots). The way date is displayed will change, but time seems to have no effect. In JIRA all changes have taken place correctly.

      Workaround

      There's no workaround at the moment.

        1. Agile-incorrect.png
          Agile-incorrect.png
          102 kB
        2. JIRA-correct.png
          JIRA-correct.png
          104 kB

            Assignee:
            Unassigned
            Reporter:
            Ana Retamal
            Votes:
            4 Vote for this issue
            Watchers:
            7 Start watching this issue

              Created:
              Updated:
              Resolved: