Summary
According to this document, change requests appear on the change calendar based on the data in four fields:
- Planned start or Planned start date – when the change request is planned to start.
- Planned end or Planned end date – when the change request is planned to finish.
- Actual start or Change start date – the actual date and time the change started.
- Actual end or Change completion date – the actual date and time the change ended.
If all four fields are filled out, the change request will show on the calendar based on the data in the actual fields.
Suggestion
It would be great if we had a feature where we could choose the fields that would show requests in the Change Calendar. For example, showing requests based on planned fields(Planned start and Planned end).