Priority is always set to "Highest" in the target Project when "Create Linked Issue" is used

    XMLWordPrintable

Details

    Description

      NOTE: This is for JIRA Server.

      Issue Summary

      Priority is always set to "Highest" in the target Project when "Create Linked Issue" is used
       

      Steps to Reproduce

      1. Create two Projects, One should be Service Desk type.
      2. Make sure the Default Priority is "Low" from the priorities section
      3. Go to the Service Desk project and hide the Priority field from the Field configuration.
      4. Create a ticket in Service Desk project
      5. Click on "Create linked issue" button and create a ticket to the second project
      6. You should see the priority will be set to "Highest" or "Blocker

      Expected Results

      The priority should be set to "Low" as the default based on the global setting.

      Actual Results

      The priority is set to "Highest" or "Blocker"
      If you show the priority field in the Service Desk project, it will set the priority correctly. Only when you hide the field, JIRA is setting the priority to Highest value for the hidden Priority.

      Workaround

      Create the ticket first in the targeted project then Link using the "Link" section

      Attachments

        Issue Links

          Activity

            People

              Unassigned Unassigned
              96194978d17e aalagappan
              Votes:
              14 Vote for this issue
              Watchers:
              12 Start watching this issue

              Dates

                Created:
                Updated: