In time tracking if I estimate 80 hours (which, for me is two work weeks or 10 days), JIRA changes it to 3 days 8 hours (1 day = 24 hours). We work 8 hour days, 5 day weeks. Would it be possible to set up the conversion for display for hours/days/weeks through a configuration of some kind. Say that 1 day = 8 hours, 1 week = 5 days.
A configuration option might be confusing because all the display times would change if the configuration changed. But, what if the configuration can only be changed/setup when activating time tracking...
- duplicates
-
JRASERVER-879 Jira should preserve original work estimate
- Closed
- is duplicated by
-
JRASERVER-1118 Worklog to use working days/weeks etc.
- Closed