-
Bug
-
Resolution: Duplicate
-
Low
-
None
-
6.0.1/OD-15
-
6
-
The attached screenshot was taken from a parent task that has four subtasks. None of the issues involved has any original estimate or work logged. One of the four subtasks has a resolution. The parent task has a section that displays information about the Subtasks, and it is configured to show all the subtasks.
What is seen: the green Progress bar is halfway across the graphic
What was expected: the green Progress bar should be a quarter of the way across the graphic
- duplicates
-
JRASERVER-31552 Subtask progress bar broken, always stuck at 50%
-
- Closed
-