Completed subtask graphic is incorrect

XMLWordPrintable

    • 6

      The attached screenshot was taken from a parent task that has four subtasks. None of the issues involved has any original estimate or work logged. One of the four subtasks has a resolution. The parent task has a section that displays information about the Subtasks, and it is configured to show all the subtasks.

      What is seen: the green Progress bar is halfway across the graphic

      What was expected: the green Progress bar should be a quarter of the way across the graphic

            Assignee:
            Unassigned
            Reporter:
            MattS
            Votes:
            0 Vote for this issue
            Watchers:
            2 Start watching this issue

              Created:
              Updated:
              Resolved: