Enabling "Only show Sprints in this project" checkbox still displays different projects in the "Recent Sprints" section of the Sprint Field.

XMLWordPrintable

    • Type: Bug
    • Resolution: Fixed
    • Priority: High
    • Component/s: Backlog - Sprints
    • None
    • 4
    • Severity 3 - Minor
    • 2

      Problem

      There is a checkbox to only display Sprints in the opened project in the Sprint Field. Yet, even with that option enabled, the "Recent Sprints" will show sprints in other previously selected projects.

      Steps to Reproduce

      1. Create two sprints in different projects.
      2. Open an issue in Project A, and populate the Sprint Field with a sprint from this Project A.
      3. Open an issue in Project B, and click on the Sprint Field. Then activate the checkbox "Only show sprints in this project."

      Expected Results

      It should display the Active, Future, and Recent sprints associated only with project B.

      Actual Results

      As the attachment demonstrates, it will incorrectly display the last sprint chosen in Project A.

      Workaround

      Currently, there is no known workaround for this behavior. A workaround will be added here when available.

            Assignee:
            Daniel Young
            Reporter:
            Victor Rondon (Inactive)
            Votes:
            11 Vote for this issue
            Watchers:
            19 Start watching this issue

              Created:
              Updated:
              Resolved: