Summary
When Capacity is overloaded it is not indicated by the Red overbooked portion as described in:
- https://confluence.atlassian.com/display/JIRAPortfolioServer/Using+the+capacity+view
You've planned your sprint on the agile board, but the total capacity exceeds the team's velocity. In this case, the capacity view shows the red overbooked portion.
Environment
- JIRA Server 7.2.X and later
- Portfolio 2.1.3
Steps to Reproduce
- Set up Portfolio Plan that is over capacity
- Calculate plan
Expected Results
Red overbooked portion Shown indicating over allocated resources in plan:
Actual Results
does not indicate any over allocated resources:
NOTES:
- Works in Current JIRA Cloud v1000.526.2 + Portfolio
- Works in JIRA 7.1.X and below + Portfolio 2.1.3
Workaround
There is no workaround at this time