Type:
Bug
-
Resolution: Unresolved
-
Priority:
Low
-
None
-
Affects Version/s: 2.0.2, 2.2.2, 3.2.0, 3.3.1, 3.4.1, 3.5.1
-
Component/s: None
-
6
-
Severity 3 - Minor
-
0
NOTE: This bug report is for JIRA Portfolio Server. Using JIRA Portfolio Cloud? See the corresponding bug report.
When creating a plan based off of a board with an active sprint, issues are included in plan even though they are not selected on the Scope page when configuring issue source.
- These issues are "Done" status and do not appear on the Scope page at all.
Steps to reproduce
- Create JIRA Software Scrum Software Development project, add sprint
- Create issue and add to sprint, start sprint and then change issue status to "Done"
- Create plan using scrum board as source (use default selections on releases, teams, and scope pages)
- On the "Confirm what's in scope" page, note no issues appear and "0 selected"
- Expand "Issues without parent Epic" and note that the "Done" issue was included in plan.
Expected Behavior
Creating a plan with "0 selected" on the Scope page should create a plan that contains no issues.
- These "Done" issues should either not be included in the new plan or they should show up on the Scope page so that they can be selected or un-selected
Workaround
After you create the plan you can exclude the "Done" issues. You can do this by checking the issue box and clicking "Exclude from plan".
- is related to
-
JPOSERVER-1442 Import wizard in live plans should show that completed issues are imported
- Gathering Interest
-
JPOSERVER-1597 Include the same filters in the Select scope page of wizard as the backlog
- Gathering Interest
- relates to
-
JRACLOUD-88557 Done issues in active sprint not showing in issue source but are still added to plan
-
- Closed
-
- is cloned by
-
JPOS-5122 Loading...
- mentioned in
-