Done issues in active sprint not showing in issue source but are still added to plan

XMLWordPrintable

    • Severity 3 - Minor

      NOTE: This bug report is for JIRA Portfolio Cloud. Using JIRA Portfolio Server? See the corresponding bug report.

      When creating a plan based off of a board with an active sprint, issues are included in plan even though they are not selected on the Scope page when configuring issue source.

      • These issues are "Done" status and do not appear on the Scope page at all.
      Steps to reproduce
      1. Create JIRA Software Scrum Software Development project, add sprint
      2. Create issue and add to sprint, start sprint and then change issue status to "Done"
      3. Create plan using scrum board as source (use default selections on releases, teams, and scope pages)
        • On the "Confirm what's in scope" page, note no issues appear and "0 selected"
      4. Expand "Issues without parent Epic" and note that the "Done" issue was included in plan.
      Expected Behavior

      Creating a plan with "0 selected" on the Scope page should create a plan that contains no issues.

      • These "Done" issues should either not be included in the new plan or they should show up on the Scope page so that they can be selected or un-selected
      Workaround

      After you create the plan you can exclude the "Done" issues. You can do this by checking the issue box and clicking "Exclude from plan".

            Assignee:
            Unassigned
            Reporter:
            Tim Evans (Inactive)
            Votes:
            1 Vote for this issue
            Watchers:
            3 Start watching this issue

              Created:
              Updated:
              Resolved: