Issue Summary
After Delete and re-adde anchor sprints in a Program Increment, synced scrum boards are showing as "not generated" despite the Features and Stories appearing to have the correct sprints. Attempts to resync using various methods have not resolved the issue, resulting in Features not displaying in the correct sprints on the boards, with some remaining in the unassigned backlog.
This is reproducible on Data Center: (yes)
Steps to Reproduce
- create PI
- create Sprints
- create Feature
- create Stories
- assign Stories to sprints
- assign Feature to Anchor date
- delete Anchor date of Feature
-
Expected Results
The Feature are not supposed to be removed from Program Board
Actual Results
The features were removed from the Program Board
Workaround
- Clean up old data
- delete the sprints that were made orphan of PI if they still exist
- for the children Stories, remove them from the Team
- for the children Stories, remove them from Sprint
- create the new anchors and Sprints if needed
- add the children's Stories to the correct Team and Sprint
- Stories should be visible once again on Program Board to be added to the right Sprint
awww no! My screenshots didn't take!