Issue Summary
The data is present on [Feature Process Step Assignment History].[Assignment End Date] for the first Step of the list related to a Feature will display the value as "9999-12-31 00:00:00.000" instead of the correct date when this was transitioned. See one example below:
feature id | feature name | process step name | Assignment Start Date | Assignment End Date |
---|---|---|---|---|
1197 | Diego Test Feature with Changes on Process Step 1 | New 1 | 2023-04-17 17:24:11.307 | 9999-12-31 00:00:00.000 |
1197 | Diego Test Feature with Changes on Process Step 1 | Review | 2023-04-17 17:25:05.860 | 2023-04-17 17:25:05.867 |
1197 | Diego Test Feature with Changes on Process Step 1 | In Progress | 2023-04-17 17:25:05.867 | 9999-12-31 00:00:00.000 |
Steps to Reproduce
- Create a Feature that has Process Steps
- Now move it to a next step
- Query the view [Feature Process Step Assignment History] and see the [Assignment End Date] for the first step
Expected Results
[Assignment End Date] would show the date when the first step was moved to something else.
Actual Results
[Assignment End Date] shows the date of the first transition as "9999-12-31 00:00:00.000"
Workaround
Currently there is no known workaround for this behavior. A workaround will be added here when available