Uploaded image for project: 'Jira Align'
  1. Jira Align
  2. JIRAALIGN-4501

Forecast: 'Total Team Capacity' displays under the wrong team

    XMLWordPrintable

Details

    • 2
    • Severity 2 - Major
    • No

    Description

      Issue Summary

      This is reproducible on Data Center: (yes)

      On the Forecast report, when selecting more than 1 program related to the same PI and different teams the  'Total Team Capacity' value shows up in the wrong team. The report works fine with only one program and a PI selected

      Steps to Reproduce

      Prerequisites:

      *A PI

      • Two programs with different teams
      • Epics with MW values filled 
      1. Select a single program and a related PI
      2. Access the Forecast page/report and change the 'View Type' to 'Agile by team'
      3. Notice that the values of the Epics show up correctly under the single team related
      4. Select the other program (that has the same PI but a different team)
      5. Notice that the value that was showing up for the 1st team is now showing under the second team selected

      Expected Results

      MW values keep their consistency when applying a non-related program/team on T1

      Actual Results

      MW values that was showing up for the 1st team is now showing under the second team selected

      Workaround

      Currently there is no known workaround for this behavior. A workaround will be added here when available

      Attachments

        Issue Links

          Activity

            People

              dfuller@atlassian.com Don Fuller
              cb9f299998cb Alessandra Garcia
              Votes:
              0 Vote for this issue
              Watchers:
              5 Start watching this issue

              Dates

                Created:
                Updated:
                Resolved:

                Backbone Issue Sync