Issue Summary
In the "Story Point Progress by Team" report, some teams' "Planned Points" columns in the chart do not match the number displayed when you mouse over, in some cases (see attachments as an example).
Steps to Reproduce
- Go to Reports > "Story Point Progress by Team"
- Select one Portfolio which contains several teams
Expected Results
All the points drawings must show the same values as the numbers displayed when the mouse is over.
Actual Results
The columns for "Points Planned" do in some cases not match with the number shown when mousing over the column (see attachments as an example).
Workaround
Currently, there is no known workaround for this behavior. A workaround will be added here when available
- is duplicated by
-
JIRAALIGN-4777 Story Point Progress by Team Report: Issues if selected PI has sprints start/end dates in different years
- Closed
- mentioned in
-
Page Loading...
- resolves
-
ALIGNSP-15148 Loading...