Capacity Planning Table returns totals as 0 value

XMLWordPrintable

      Issue Summary

      In the Capacity Planning report, when viewing the bottom chart as a Table, all Total values apart from Hours Planned return 0 regardless of actual available sum.

      Steps to Reproduce

      1. Add Team Members and Member allocation to a new or existing sprint.
      2. Check Capacity Planning report and switch lower report to View as Table

      Expected Results

      Table shows Total row with sum total values

      Actual Results

      Table shows all but Hours Planned as 0 value

      Workaround

      Currently there is no known workaround for this behavior. A workaround will be added here when available

            Assignee:
            Anna Eshlin De Kassal (Inactive)
            Reporter:
            Jose Sanchez
            Votes:
            1 Vote for this issue
            Watchers:
            5 Start watching this issue

              Created:
              Updated:
              Resolved: