Type:
Suggestion
-
Resolution: Fixed
-
Component/s: Dynamic Reports - Legacy Roadmap
-
2
Issue Summary
Features
The start and end dates for features are based on dates set on the object in the following priority order:
- If a feature has a target start and end date set, they are rendered based on those dates.
- If a feature does not have a target start and end date set, they are rendered based on the target start and target end sprint.
- If a feature does not have either date, they are rendered according to the dates of the PI(s) assigned to it.
However, testing the scenario: "If a feature does not have a target start and end date set" does not display with "target start and target end sprint", but instead with PI dates.
Steps to Reproduce
- Feature 9452 alignsupport
PI Start PI End Target Sprint Start Date Target Sprint End Date Dates: Start/Initiation Dates: Target Completion Roadmap Start Roadmap End Outcome Roadmap is using... 1 Oct 31 Dec 29 Oct 11 Nov 1 Dec 14 Dec 1 Dec 14 Dec 1 Dec - 14 Dec Dates 1 Oct 31 Dec 29 Oct 11 Nov blank blank 1 Oct 31 Dec 1 Oct - 31 Dec PI 1 Oct 31 Dec blank blank 1 Dec 14 Dec 1 Dec 14 Dec 1 Dec - 14 Dec Dates blank blank blank blank 1 Dec 14 Dec not visible not visible not visible not visible
Expected Results
Features
The start and end dates for features are based on dates set on the object in the following priority order:
If a feature has a target start and end date set, they are rendered based on those dates.
If a feature does not have a target start and end date set, they are rendered based on the target start and target end sprint.
If a feature does not have either date, they are rendered according to the dates of the PI(s) assigned to it.
Actual Results
Features
The start and end dates for features are based on dates set on the object in the following priority order:
If a feature has a target start and end date set, they are rendered based on those dates.
If a feature does not have a target start and end date set, they are rendered based on the target start and target end sprint.
If a feature does not have either date, they are rendered according to the dates of the PI(s) assigned to it.
Workaround
Set the target start and end date.