Description
Issue Summary
Change of dates in generated anchor sprints does not prompt to update the Allocations. Has flow-on impact to other areas.
Steps to Reproduce
- Open Program Increments https://xyz.jiraalign.com/ProjectGrid
- Create a new Program Increment by clicking on "Add New Program Increment"
- Click on Tab "Sync Sprints"
- Leave the duration as the default of 1 week (5)
- Create Anchors
- Change the dates on the Anchors created (because "I really wanted 2 weeks duration") to 2 week length
- Save
- Generate Team Iterations (or sync with Connector)
- Click on cog icon next to an Anchor Sprint
- Click on "Iteration Found"
- Opens new window of https://xyz.jiraalign.com/IterationGrid called "Sprint List" with the Sprint flyaway panel opened.
- Click on Members tab
- Add a Member in, with Role Developer, Task Allocation = 100%
- Save
- Now open Program Increment Allocation Report https://xyz.jiraalign.com/ReleaseProductUserReport
- Confirm you are in the correct Program Increment (for the Sprint)
- View the Planned Hours for the Member that you added.
Expected Results
Planned Hours for the Member will be 2 week's worth.
Actual Results
Planned Hours for the Member will only be one week's worth.
Workaround
Manual update. Which will work for small numbers of sprints, but not for larger numbers.