    Description

      Problem

      Scrum Master can change a story's sprint  assignment during an in-progress sprint.

      • This issue is only for In Progress Sprints.
      • In the Team Room, a Scrum Master for the Sprint cannot change the Sprint for a specific Story.
      • The warning message is: Sprint is in progress. Only a team coach can change this 

       

      Steps to Reproduce

      1. The System Role needs to be RTE
      2. The Sprint Role needs to be Scrum Master
      3. In Team Room try to click on Story with a Sprint in Progress.
      4. Try to change the Sprint for the story, you will not be allowed (grayed out).
      5. Hover over the warning sign and it says: Sprint is in progress. Only a team coach can change this

      Expected Results

      Per our documentation, Scrum Master should be able to make this change.

      Actual Results

      The warning message is: Sprint is in progress. Only a team coach can change this 

      Workaround

      • If we change the Sprint Role from Scrum Master to Team Coach, then the issue is fixed.
      • Another workaround is to drop the Story; this allows the Scrum Master to make change the Sprint in the Story.

      Notes

      Attachments

        Issue Links

          Activity

            People

              cgottlieb@atlassian.com Caz (Inactive)
              0780b5d3ccc0 Mario Sojo
              Votes:
              0 Vote for this issue
              Watchers:
              6 Start watching this issue

              Dates

                Created:
                Updated:
                Resolved:

                Backbone Issue Sync