Bug
-
Resolution: Fixed
-
Medium
-
10.68
-
None
-
1
-
Severity 2 - Major
-
Batman! - TART1
Issue Summary
Work in Process by State > Lean Metrics > Lead Time utilizes incorrect formulas for Epics
Steps to Reproduce
- Work in Process by State > Lean Metrics > Lead Time
- View the Lead Time graph for Epics
Expected Results
The Epic view of Lead Time should be a rolling history of the average time it takes for all Epics in a PI to be accepted/done. The 'clock' starts when the item is created and ends when it moves accepted/done (plus 1 day).
For example, if the item was created on July 7 and moves to done on July 9, the lead time July 9 - July 7 + 1 = 2 + 1 = 3 days.
Actual Results
The Epic view utilizes the story calculations
Workaround
No workaround at this time. A workaround will be published if one is found.
- resolves
-
ALIGNSP-2665 Loading...