[JIRAALIGN-1212] Status Of Team Experiments: Prior Iteration Experiments / Actions from legacy sprints can not be marked Done or Abandoned

XMLWordPrintable

    • Icon: Bug Bug
    • Resolution: Fixed
    • Icon: Low Low
    • 10.69
    • 10.65
    • team - teams
    • None
    • 1
    • Severity 3 - Minor
    • Party Parrots - RHP9

      Issue Summary

      Status Of Team Experiments: Prior Iteration Experiments / Actions from legacy sprints can not be marked Done or Abandoned

      Steps to Reproduce

      1. Run a Sprint Retrospective and Agree on Action Plans for the next iteration
      2. Run a Sprint Retrospective for the Subsequent sprint and keep an Action Item from the original sprint
      3. Run a Sprint Retrospective for the next Sprint
      4. Check the Status of Team Experiment Reports for the Team associated to the Retrospectives

      Expected Results

      There would be an option to mark Kept Actions as Done/Abandoned on the Status of Team Experiments Report

      Actual Results

      The Action item that was kept from Sprint 2 shows as "This action has yet to be implemented" on the Status of Team Experiments Report with no option to mark it as Done/ Abandoned

      Workaround

      Carry over kept Action items from one Sprint Retrospective to another by adding them as a new Action Plan for the next Sprint

              kforeman@atlassian.com Kyle Foreman
              tkeyes@atlassian.com Tim Keyes
              Votes:
              0 Vote for this issue
              Watchers:
              5 Start watching this issue

                Created:
                Updated:
                Resolved: