Completed Issue Type = Story point values are not showing up in Sprint Report nor Velocity Report

    XMLWordPrintable

Details

    • Bug
    • Resolution: Duplicate
    • High
    • None
    • 6.3.1
    • AgileBoard

    Description

      To replicate:
      Add Stories to current sprint
      Start Sprint
      Create Sub-tasks
      Complete Story
      View Sprint Report
      Completed Stories show value of

      See attached screen capture.

      This has now become a major reporting issue and a black eye for me with the PMO who is apprenhesive to Agile and we were using Jira Agile and it's Sprint and Version reports to demonstrate how well we can predict completion dates vs using Clarity or MS Project. Now I do not know how to explain this problem. Pease let me know how to fix or if it is user error.

      Attachments

        Issue Links

          Activity

            People

              Unassigned Unassigned
              6a4248dbd428 Ricardo Henao
              Votes:
              1 Vote for this issue
              Watchers:
              3 Start watching this issue

              Dates

                Created:
                Updated:
                Resolved: