I as a Product Owner or Scrum Master want to see a report generated by Greenhopper/JIRA Agile which shows the projected completion for the current backlog items so that I can better understand what the overall project status is today.
Further thoughts:
- able to select which epics to include as "total backlog"
- calculation based on story points
- configurable average velocity (how many or which past sprints to consider for average)
- utilize average velocity to calculate projected completion
- show how many sprints until completed
- show optimistic and pessimistic line
- configurable optimistic and pessimistic calculation (percentage)
I'm doing this today in Excel based on data I'm extracting out of JIRA.
This is the most important chart for our project and helps everybody involved to better understand where we at and take actions early to influence the project for the better.
Attaching an image of the chart I'm creating in Excel at the moment.
[JSWSERVER-9634] Line chart for projected backlog completion with optimistic and pessimistic
Workflow | Original: JAC Suggestion Workflow [ 3066899 ] | New: JAC Suggestion Workflow 3 [ 3661348 ] |
Status | Original: RESOLVED [ 5 ] | New: Closed [ 6 ] |
Workflow | Original: Confluence Workflow - Public Facing v4 [ 2625179 ] | New: JAC Suggestion Workflow [ 3066899 ] |
Workflow | Original: JIRA PM Feature Request Workflow v2 - TEMP [ 2327213 ] | New: Confluence Workflow - Public Facing v4 [ 2625179 ] |
Status | Original: Closed [ 6 ] | New: Resolved [ 5 ] |
Workflow | Original: JIRA PM Feature Request Workflow v2 [ 2044037 ] | New: JIRA PM Feature Request Workflow v2 - TEMP [ 2327213 ] |
Workflow | Original: JIRA PM Feature Request Workflow v2 - TEMP [ 2032200 ] | New: JIRA PM Feature Request Workflow v2 [ 2044037 ] |
Workflow | Original: JIRA PM Feature Request Workflow v2 [ 736220 ] | New: JIRA PM Feature Request Workflow v2 - TEMP [ 2032200 ] |
Business Value | Original: Exceptional [ 10503 ] | |
Workflow | Original: GreenHopper Kanban Workflow v2 [ 549065 ] | New: JIRA PM Feature Request Workflow v2 [ 736220 ] |
Issue Type | Original: Story [ 16 ] | New: Suggestion [ 10000 ] |
Priority | Original: Major [ 3 ] | |
Status | Original: Resolved [ 5 ] | New: Closed [ 6 ] |
Epic Link | New: JAGDEV-905 [ 319776 ] |
Resolution | New: Answered [ 9 ] | |
Status | Original: Open [ 1 ] | New: Resolved [ 5 ] |
Many thanks for reporting this issue. As mentioned earlier here, this functionality is partially supported by today's Epic and Version reports. We are looking at improving them in the near future, specifically one of the improvements we're looking for is using sprint velocity to project how many sprints are left to complete a Version or an Epic.
Please keep an eye on those improvements in the upcoming releases of JIRA Agile, and let us know if they meet your requirements.
Kind regards
Tom Kotecki
Product Manager, JIRA Agile