When trying to complete a sprint that has unresolved sub-tasks, instead of automatically removing these issues to the backlog Greenhopper gives error:
"Sprint cannot be completed as there are incomplete subtasks in the following issue: ..."
Workarounds:
There are two possible workarounds for this problem:
- Manually remove those from the sprint - https://confluence.atlassian.com/display/GH/Removing+an+Issue+from+a+Sprint
or - Close off the subtask issue that's caught, then reopen it to put it in the next sprint
- duplicates
-
JSWSERVER-9418 JIRA 6.1: cannot complete sprint with open subtasks on open issue
- Closed
- is duplicated by
-
JSWSERVER-9513 Starting a new sprint does not close the previous sprint
- Closed
- is related to
-
JSWSERVER-7232 Unable to complete a sprint if sub-task status is not included in the Done column
- Closed
-
JSWSERVER-9525 Remove issue from a Sprint not working on Work Mode
- Closed
- relates to
-
JSWCLOUD-9512 Unable to complete sprint because sub-task is not resolved
- Closed
-
JSWSERVER-12012 Unable to close Sprint with closed parent issue and open sub-tasks
- Closed
- links to