Uploaded image for project: 'Jira Software Data Center'
  1. Jira Software Data Center
  2. JSWSERVER-7359

Resolving a subtask on the kanban board falsely claims that all other subtasks are done if they're not on the board

XMLWordPrintable

    • Icon: Bug Bug
    • Resolution: Duplicate
    • Icon: Medium Medium
    • None
    • 6.1.2
    • None

      on JAC:

      dragged a subtask to "done", got a dialog telling me that all subtasks of the parent are done and asking if I want to match the parent. This is not correct, the other subtasks were still open, they were not on the board though (neither was the parent).

              Unassigned Unassigned
              ahennecke Alex Hennecke (Inactive)
              Votes:
              0 Vote for this issue
              Watchers:
              3 Start watching this issue

                Created:
                Updated:
                Resolved: