Details
-
Bug
-
Resolution: Fixed
-
Medium
-
5.10, 6.0.1
-
None
-
5.1
-
Description
Steps to Reproduce:
Create an issue with an original estimate of 8 hours. The log work for 8 hours, automatically adjusting remaining estimate.
Current status should be 8h Original Estimate (OE), 8 Hours Time Spent (TS), 0 Hours Remaining Estimate (RE)
Now log work again, this time working 1 hour and adjusting the RE to 2h.
Then edit that work log, so that the 1 hour worked is now 2.5, and the RE is 0.5h instead of 2h.
Now create a new sprint and add just this issue to it.
Expected Behaviour:
As of the last update before being added into the sprint, the issue had 30minutes remaining. I would expect the RE to be 30 minutes in the Burndown Chart
Actual Behaviour:
It will end up being reporting as having negative 1.5 hours remaining.
Other info:
Michael R says it's possibly because it's parsing the edited entry and not the other change.