As a Kanaban team lead I want to limit my WIP (work-in-progress) for each column on the taskboard. Further, the work items for our team vary in size and therefore we use story points as a measure of effort required for each item. Given this workflow it would be helpful if we could set column constraints that were based on the total number of story points for all issues in a given column.
- is related to
-
JSWSERVER-4917 Allow Column Constraint to be set to any numeric field (i.e Story Points)