Incorrect Calculations for Required Daily Burnup Rate

    XMLWordPrintable

Details

    • Bug
    • Resolution: Handled by Support
    • Medium
    • 5.7.2
    • 5.2 (JIRA 4.1 Compatible)
    • None

    Description

      The Burnup Chart miscalculates the required daily burnup rate and doesn't match rate from required daily burdown rate (from burndown chart). Something is broken in the way the burnup chart calculates the required daily burnup. See the attached file for an example chart that miscalculates the wrong burnup rate - Starts at 2, drops to 0!, slowly increases, but math doesn't work - 13 points and 6 days remaining in sprint, but calculation says daily burnup rate of 4 points required! Also, "ongoing" story point dotted line shows we're closing 2 points soon, but that makes "ongoing" burnup rate jump to 5 points required! Something's very wrong with this calculation.

      Attachments

        Activity

          People

            Unassigned Unassigned
            0a5eb79807e6 Ian Colle
            Votes:
            0 Vote for this issue
            Watchers:
            1 Start watching this issue

            Dates

              Created:
              Updated:
              Resolved: