Details
-
Bug
-
Resolution: Won't Fix
-
Low
-
None
-
5.4, 5.5, 5.6
-
None
-
5.04
-
Description
From https://studio.atlassian.com/browse/JST-3848
This bug appeared on 14.2.2010, after the update on 13.2.2010.
Go to Task Board, select version X and developer D.
Change the version of a task to version Y.
The filter changes to version Y and no developer is selected (filter to All Assignees).Was working fine until at least 11.2.2010, where the behaviour was that the flter stayed in place an a little message said something that "you can't view the message you were working on because it is not in the filter".
The current behavior is really annoying because you have to get back to the version you were working on.
Using the planning board is not an option because you cannot filter on the developer.
Attachments
Issue Links
- is duplicated by
-
JSWSERVER-2859 Keep the Task Board in the current sprint when changing the sprint of one issue
- Closed
- relates to
-
JSWSERVER-2881 Investigate: Log work operation of a task in the task board redirect the page to "ALL Assignee".
- Closed