Hi,
I might have chosen the wrong component. Sorry for that. Maybe you could choose the right component for me or add a comment with the right component so I can add it. Here is my suggestion/ request:
We use the PI Roadmap in Jira in our project and regularly take a look at the dependency bubbles in the roadmap.
Among other use cases a dependency bubble turns red if the lead time of two issues with a "has to be started together"-dependency is different.
I don't know the idea of the lead time but we usually create an issue during a running PI and plan the implementation in the next PI planning. So the lead time is not necessary for our plan which is why I wanted to ask:
Is there a possibility to deactivate the consideration of the lead time for the automatic Jira evaluation of a dependency risk?
In the PI roadmap scheduling settings for dependencies I can only choose between concurrent or sequential scheduling and I already chose concurrent but the dependency bubble is still red due the different lead time...
If the deactivation is not possible, yet is it planned? I couldn't find it on my search.
Thank you very much in advance for your help.