Type:
Bug
-
Resolution: Fixed
-
Priority:
Low
-
Affects Version/s: 9.12.16, 10.5.0
-
Component/s: Reports
-
9.12
-
2
-
Severity 2 - Major
-
28
Issue Summary
Burnup report doesn't consider updates on Story Points
This is reproducible on Data Center: (yes)
Steps to Reproduce
- Start a Sprint with estimated issues
- Change the estimation of one of the cases
- Close the issue, the report will increase the completed work using the original estimation
Estimation changed from 1 to 2, which reflects in the sprint report:-
Burnup chart doesn't considers updates on story points and displays only 1 as a completed story point
Expected Results
The Burnup report reads the new estimation
Actual Results
Burnup consider the original estimation
Workaround
Currently there is no known workaround for this behavior. A workaround will be added here when available