Filtering the Scheduled Range on Advanced Roadmaps' Program Schedule view doesn't apply as expected

XMLWordPrintable

      Issue Summary

      Filtering the Scheduled Range on Advanced Roadmaps' Program Schedule view doesn't apply as expected.

      If you apply a filter to the dates the view will still always show all elements found by the other filters. If you have a very large Epic or Initiative that would limit your ability to narrow down with the date filters and it would always show the large Epic.

      This is reproducible on Data Center: yes

      Steps to Reproduce

      • Create a program and a plan.
      • Within the Plan, create an epic with an Story inside it.
      • Set the start and end date of both Epic and Story to be a couple months apart, let's say October/24 to February/25.
      • Go to the Program view, Schedule tab.
      • Click the drop-down More and select Scheduled Range.
      • On the Scheduled Range drop-down that appeared, select a start date and end date within December for the Specific range.

      Expected Results

      You would be presented with a filtered view, showing only the date range selected.

      Actual Results

      The view will not reduce further than the minimum size needed to display the Epic.

      Here are a couple screenshot to clarify the behavior:

      Unfiltered view:

      Date provided:

      View after the filter was applied (unchanged since it tries to fit the full Epics:

      Workaround

      Currently there is no known workaround for this behavior. A workaround will be added here when available