Problem Statement
When the active sprint ended and created a new sprint, the new sprint will not be automatically started. For example:
This is an intended design where the new sprint will not auto start and require user to manually schedule the sprint.
Workaround
Create multiple sprints (example create 10 new sprints ahead) and schedule the date in the start and end date of each new sprints. Then, select the following each sprint in the "After sprint completes, move open issues to:" field value. This way the sprint will be auto start and ended.
Suggestion
Allow auto start for new sprint option.